UPCOMING PROJECTS:
NovaChip paving will take place in the following neighborhoods:
Hunters Crossing, Sweetbriar, Hallmark Pl., and Timberbrook Dr.
1st week of April – Crack Sealing in areas where needed.
3rd week of April – Spot Chip Patching in areas and milling where needed.
3rd/4th week of April – Placing risers in catch basins (inlets) and manholes (other prep work as needed)
4th week of April/1st week of May – begin paving.
All dates are subject to change due to weather conditions, equipment issues, or other unforeseen circumstances.
The paving process will take approximately 2 weeks total to complete all areas.
AMS will hand out notification papers to all affected residents prior to the paving process. They will also be posting the streets for NO PARKING when applicable.